Buy-to-Let Property Preparation — Professional Report – £300–£600/sqm
Prepared for Julianah Howusu • julianahowusu@gmail.com
Estimated Total Cost
£59400
Estimated Duration
13 weeks
Contingency
10%

The estimated total cost for the Buy-to-Let property modernisation is £59,400 including VAT and a 10% contingency. The project is expected to take approximately 13 weeks to complete. The property, spanning 110sqm (about 1184 sqft), will undergo comprehensive updates including new kitchen and bathroom installations, laminate and carpet flooring, and modern decoration throughout. The estimated cost per square foot is £45, rendering it a viable investment under the specified budget. The project aligns with standard quality specifications, promising enhanced market appeal.

Detailed Cost Analysis

CategoryDetailsTotal
Flooring
Laminate flooring installation downstairs — £3500
Carpet installation upstairs — £2500
Note: Includes laminate flooring for ground floor and carpet for upper floor.
£6000
Kitchen
New kitchen installation including tiling — £16500
Note: Standard kitchen fitting with 10 sqm of tiling.
£16500
Bathroom
New bathroom installation with fixtures — £11000
Note: Includes installation of 3 bathroom fixtures.
£11000
Electrical
Minor electrical updates — £3300
Note: Minor updates to existing electrical system.
£3300
Decoration
Modernisation and decoration throughout — £17600
Note: Comprehensive modernisation and decoration.
£17600
Subtotal£54000
Contingency (10%)£5400
Grand Total£59400
Cost Distribution
Chart: Cost by Category
Materials vs Labour
Chart: Materials vs Labour

Material Specifications & Procurement

Materials
ItemSpecificationQtyUnitSupplier
Laminate FlooringStandard Oak, 8mm thickness60sqmHowdens
CarpetWool blend, plush pile50sqmCarpetright
Kitchen UnitsModern white gloss, soft-close1setWren Kitchens
Bathroom FixturesStandard porcelain, chrome taps3piecesVictoria Plum
TilesCeramic white, 30x30 cm10sqmTopps Tiles
Emulsion PaintMatt finish, various colours50litresDulux
Lead Times
ItemLead Time (days)
Laminate Flooring10
Carpet14
Kitchen Units21
Bathroom Fixtures14
Tiles7
Paint5
Chart: Lead Times (days)

Supplier Directory & Compliance

Supplier Directory
SupplierNoteWebsite
HowdensPreferred for flooring and kitchen units.https://www.howdens.com
CarpetrightCommon choice for carpets.https://www.carpetright.co.uk
Wren KitchensSpecialist in kitchen units.https://www.wrenkitchens.com
Victoria PlumReputable supplier for bathroom fixtures.https://www.victoriaplum.com
Topps TilesProvides a wide selection of tiles.https://www.toppstiles.co.uk
*Other suppliers are available.
Trade Discounts
SupplierDiscount
Howdens10%
Wren Kitchens12%
Carpetright15%
Topps Tiles7%
Planning & Building Regulations
Planning Permission: Typically not required unless structural changes or external appearance are affected.
TopicRequirement
Fire SafetyMust comply with Part B of the Building Regulations.
Sound InsulationAdhere to Part E requirements.
Electrical SafetyConform to Part P standards.
VentilationEnsure adequate ventilation as per Part F.
Energy EfficiencyMeet minimum standards under Part L.

Money-Saving Strategies & ROI

Strategies
  • Bulk buying materials to secure discounts.
  • Scheduling trades to minimise downtime.
  • Utilising trade discounts from key suppliers.
  • Implementing energy-efficient installations for long-term savings.
  • Choosing standard specifications to control costs.
  • Reusing existing materials where possible to reduce expenses.
ROI Waterfall
Chart: ROI Waterfall
ROI Summary
Chart: ROI Summary
*Although not guaranteed, renovations can increase value by the proposed values.

Project Timeline & Implementation

Chart: Timeline (Gantt)
Trade Day Rates
TradeRate/Day
Electrician£325
Plumber£310
Decorator£295
Joiner/Shopfitter£330
General Builder£280
Labourer£200

Risk Assessment & Problem Prevention

Chart: Risk Matrix
Risks & Mitigations
RiskLikelihoodImpactMitigation
Electrical Updates RiskMediumMediumEnsure thorough inspection to pre-empt issues.
Material Cost FluctuationHighHighSecure fixed-price contracts with suppliers.
Project DelaysMediumHighImplement tight management supervision.
Supply Chain DisruptionMediumMediumSource alternative suppliers as backup.

Property Value Impact & Investment Analysis

Pre-Renovation Value£236800
Total Project Cost£59400
Post-Renovation Estimate£272280
Area (sqft) × £/sqft1184 × £45

The scope of works involves modernisation throughout with a focus on new kitchen and bathroom installations along with flooring and decoration. Standard quality materials are assumed, and plumbing relocation is not required, ensuring efficient project completion within the estimated timeframe.

Completion Checklist
  • Inspect all flooring installations for completeness.
  • Ensure all kitchen and bathroom fixtures are operational.
  • Verify that all electrical installations are compliant.
  • Produce certificates for gas and electrical works.
  • Check that decoration work meets project specifications.
  • Ensure all building regulations requirements are met.
  • Confirm that all waste is properly disposed of.
  • Conduct final clean-up and site inspection.
  • Document all construction phases as per regulatory standards.
  • Verify that all contracted works meet warranty criteria.