Retail Space Renovation — £200–£800/sqm • 1–3 months – Professional Report
Prepared for Jitedra • teste@refurbmate.com
Estimated Total Cost
£55200
Estimated Duration
9 weeks
Contingency
10%

This report outlines the renovation plan for the retail space at ABC Test Address. With an estimated cost of £55,200 including VAT and contingency, the project spans approximately 9 weeks. The area covers 100 sqm, translating to about £46 per sqft on a standard specification level. Market appeal is strong, meeting all compliance standards.

Detailed Cost Analysis

CategoryDetailsTotal
Demolition
Removal of existing fixtures and fittings — £5547
Note: Removal of existing fixtures and fittings
£5547
Electrical
Rewiring and installation of 4 lighting fixtures — £8875
Note: Rewiring and installation of 4 lighting fixtures
£8875
Flooring
Installation of new standard flooring — £11094
Note: Installation of new standard flooring
£11094
Interior Finishes
Painting and decorating — £7766
Note: Painting and decorating
£7766
Ceiling
Installation of new ceiling tiles — £6655
Note: Installation of new ceiling tiles
£6655
HVAC
Adjustment and balancing of existing HVAC system — £5547
Note: Adjustment and balancing of existing HVAC system
£5547
Contingency
Contingency for unforeseen works — £5547
Note: Contingency for unforeseen works
£5547
Subtotal£50182
Contingency (10%)£5020
Grand Total£55200
Cost Distribution
Chart: Cost by Category
Materials vs Labour
Chart: Materials vs Labour

Material Specifications & Procurement

Materials
ItemSpecificationQtyUnitSupplier
Lighting FixturesStandard4piecesScrewfix
Wall PaintEmulsion20litresB&Q
Ceiling TilesStandard acoustic100piecesTravis Perkins
FlooringLaminate100sqmHowdens
HVAC ComponentsStandard1systemPlumb Center
Electrical WiringCopper500metresCEF
Lead Times
ItemLead Time (days)
Lighting Fixtures14
Wall Paint7
Ceiling Tiles21
Flooring21
HVAC Components28
Electrical Wiring14
Chart: Lead Times (days)

Supplier Directory & Compliance

Supplier Directory
SupplierNoteWebsite
ScrewfixReliable UK supplier for building supplieshttps://www.screwfix.com
B&QDIY and home improvement specialisthttps://www.diy.com
Travis PerkinsConstruction and building materialshttps://www.travisperkins.co.uk
HowdensKitchens and joinery productshttps://www.howdens.com
Plumb CenterPlumbing supplies and serviceshttps://www.plumbcenter.co.uk
CEFElectrical wholesalerhttps://www.cef.co.uk
*Other suppliers are available.
Trade Discounts
SupplierDiscount
Screwfix10%
B&Q8%
Travis Perkins12%
Howdens15%
Plumb Center5%
Planning & Building Regulations
Planning Permission: Typically not required unless structural changes or external appearance are affected.
TopicRequirement
Fire SafetyCompliance with Part B of the Building Regulations for fire safety.
Sound InsulationPart E regulations require sound insulation for all new constructions.
Electrical SafetyElectrical installations must comply with Part P of the Building Regulations.
Energy EfficiencyEnsure compliance with Part L for energy conservation.
VentilationAdequate ventilation as per Part F of the Building Regulations.

Money-Saving Strategies & ROI

Strategies
  • Utilise trade discounts from major suppliers.
  • Schedule bulk purchases to reduce delivery costs.
  • Consider generic brands for standard materials.
  • Plan works to minimise labour downtimes.
  • Leverage reusable building materials.
  • Negotiate fixed-price contracts with trades.
ROI Waterfall
Chart: ROI Waterfall
ROI Summary
Chart: ROI Summary
*Although not guaranteed, renovations can increase value by the proposed values.

Project Timeline & Implementation

Chart: Timeline (Gantt)
Trade Day Rates
TradeRate/Day
Electrician£300
Plumber£275
Decorator£250
Joiner/Shopfitter£320
General Builder£285
Gas Engineer£340

Risk Assessment & Problem Prevention

Chart: Risk Matrix
Risks & Mitigations
RiskLikelihoodImpactMitigation
Access DelaysMediumMediumCoordinate with property management for access times.
Unforeseen Structural IssuesMediumHighConduct thorough surveys prior to commencement.
Material ShortagesLowMediumMaintain stock levels with preferred suppliers.
Weather InterruptionsLowLowPlan indoor works during unpredictable weather periods.

Property Value Impact & Investment Analysis

Pre-Renovation Value£215200
Total Project Cost£55200
Post-Renovation Estimate£246000
Area (sqft) × £/sqft1076 × £46

This refurbishment plan has been reviewed and aligns well with the market standards in East Anglia, ensuring cost-effectiveness and timely completion.

Completion Checklist
  • Verify electrical compliance certification.
  • Confirm HVAC system balancing.
  • Ensure all finishes meet specified standards.
  • Check all fixtures for operational condition.
  • Complete handover documentation.
  • Conduct final walkthrough with client.
  • Ensure waste is disposed of properly.
  • Perform final clean-up of space.
  • Review all trades for completion.
  • Collect all warranty and guarantee paperwork.